'A' alone can finish a piece of work in 8 days & 'B' can alone can do it in 12 days.How much time will be taken if both 'A'&'B' work together?
Answers
Answer:
See below.
Step-by-step explanation:
A and B together take 8 days [ Here ‘A’ and ‘B’ refers to the work done by ‘A’ and ‘B’] .
A takes 12 days .
So,
Let the work done by A ( in 1 day ) be one -twelfth(1/12) of the work done ..
so,
in 8 days =
8 × 1/12
= 8/12
So.. now we can say that A has done 1/8 of the work ..and B has done 1/B of the work .
1/A + 1/B = 1/12 [Here B refers to number days taken by B to do the work ]
1/8+ 1/B = 1/12
1/B = 1/24
[ We equate the denominators as the numerators are equal ]
No of days B takes to complete the work = 24 days ..
Hope this helps..Thank you for the request
Answer:
Step-by-step explanation:
'A' alone can finish a piece of work in 8 days
A's one day's work =
'B' alone can finish a piece of work in 12 days
B's one day's work =
Thus one day's work of A and B
Hence No of days taken by A and B to complete the work