A alone can finish a work in 40 days and B in 60 days.initially A Alone start the work.after 20 days,he left the work.in how many days B alone can finish the remaining work?
Answers
Answered by
1
Answer:
57 days
Step-by-step explanation:
above is your solution..............
Attachments:
Answered by
0
Answer:
B alone can finish the remaining work in 30 days .
Step-by-step explanation:
A can complete work in days = 40
A's 1 day work =
B can complete work in 60 days.
B's 1 day work =
A did work for 20 days
A did part of work in 20 days =
Remaining work =
B can complete work in days = 60
So, B can compete remaining work in days =
Hence B alone can finish the remaining work in 30 days .
Similar questions
Environmental Sciences,
5 months ago
English,
5 months ago
English,
10 months ago
Science,
10 months ago
Biology,
1 year ago