A alone can finish i piece of work in 42 eays. B is 20% more efficient than a and c is 40% more efficient 5hsn
b. In how many days b and c working together can finish the same piece of work.
Answers
Answered by
21
● A alone can finish i piece of work in 42 days.
In 1 day, A can do = 1/42 of the work
● B is 20% more efficient than A.
So B can work 20% faster than A.
In order to complete the work, B will take = 42 ÷ 120/100 = 42 × 100/120 = 35 days.
In 1 day, B can do = 1/35 of the work
● C is 40% more efficient than B
So C can work 40% faster than B
In order to complete the work, C will take = 35 ÷ 140/100 = 35 × 100/140 = 25 days.
In 1 day, C can do = 1/25 of the work
● Together, B and C can do in 1 day
Days required to finish the work is:
Hence, they can finish it in 14 7/12 days.
In 1 day, A can do = 1/42 of the work
● B is 20% more efficient than A.
So B can work 20% faster than A.
In order to complete the work, B will take = 42 ÷ 120/100 = 42 × 100/120 = 35 days.
In 1 day, B can do = 1/35 of the work
● C is 40% more efficient than B
So C can work 40% faster than B
In order to complete the work, C will take = 35 ÷ 140/100 = 35 × 100/140 = 25 days.
In 1 day, C can do = 1/25 of the work
● Together, B and C can do in 1 day
Days required to finish the work is:
Hence, they can finish it in 14 7/12 days.
Anonymous:
Awesome Answer
Answered by
6
Attachments:
Similar questions