Math, asked by suresh007, 1 year ago

A & B can finish a work in 10 days, B & C
15 days and A & C in 20 days. In how ma
days would B alone can finish the work?
A. 20
B.24
C. 40
D. 60​

Answers

Answered by manu8433
2

Answer:

24 days finished work

this is a answer ok