A and B alone can complete work in 9 days and 18 days respectively. They worked together. However 3 days before the completion of the work B left. In how many days the work was completed
Answers
Answered by
13
Hi user
Here's the answer
____________________________________________________________
Time taken by A = 9 days
Rate of work done in 1 day = 1 / 9 of whole work
Time taken by B = 18 days
Rate of work done in 1 day = 1 / 18 of whole work
But A leaves before 3 days of completion of work
Let the total number of days taken be " t "
Work done by A = 1 / 9 * ( t - 3 )
Work done by B = 1 / 18 * ( t )
Work done by A + Work done by B = 1
= ( t - 3 ) / 9 + ( t ) / 18 = 1
Taking LCM, we get
Multiplying by 2 we get,
= 2 ( t - 3 ) / 9 * 2 + ( t ) / 18 = 1
= 2t - 6 / 18 + t / 18 = 1
= 2t + t - 6 / 18 = 1
= 3t - 6 = 18 * 1
= 3t - 6 = 18
= 3t = 18 + 6
= 3t = 24
=> t = 24 / 3 = 8
Hence total time taken ( t ) = 8 days
____________________________________________________________
Hope my answer is correct
Have a good day :-)
Here's the answer
____________________________________________________________
Time taken by A = 9 days
Rate of work done in 1 day = 1 / 9 of whole work
Time taken by B = 18 days
Rate of work done in 1 day = 1 / 18 of whole work
But A leaves before 3 days of completion of work
Let the total number of days taken be " t "
Work done by A = 1 / 9 * ( t - 3 )
Work done by B = 1 / 18 * ( t )
Work done by A + Work done by B = 1
= ( t - 3 ) / 9 + ( t ) / 18 = 1
Taking LCM, we get
Multiplying by 2 we get,
= 2 ( t - 3 ) / 9 * 2 + ( t ) / 18 = 1
= 2t - 6 / 18 + t / 18 = 1
= 2t + t - 6 / 18 = 1
= 3t - 6 = 18 * 1
= 3t - 6 = 18
= 3t = 18 + 6
= 3t = 24
=> t = 24 / 3 = 8
Hence total time taken ( t ) = 8 days
____________________________________________________________
Hope my answer is correct
Have a good day :-)
Destroyer22:
If it is helpful please mark it as brainliest
Answered by
9
If a and b worked together than they can finish it in=1/18+1/9
=1+2/18
=3/18
=1/6
So they can finish it in 6 days but before 3 days of completion b left means they worked together for {6-3}=3 days
Now,
A and b worked for 3 days so their work is=
{1/18+1/9}×3
=1/6×3
=1/2
Now the no. Of work is 1 so
1-1/2
=1/2
Now only b works so
1/18x=1/2
X=18/2
=9
=1+2/18
=3/18
=1/6
So they can finish it in 6 days but before 3 days of completion b left means they worked together for {6-3}=3 days
Now,
A and b worked for 3 days so their work is=
{1/18+1/9}×3
=1/6×3
=1/2
Now the no. Of work is 1 so
1-1/2
=1/2
Now only b works so
1/18x=1/2
X=18/2
=9
Similar questions