Math, asked by LuckkyTanwar, 1 year ago

A and B are doing a work

Attachments:

LuckkyTanwar: can you do fast
aryanppp: mate if you want it to be solved please send the question in english in the comment section itself....
aryanppp: mate?

Answers

Answered by inhumandrowsey
0

A can do it in = 9 days

B can do it in = 12 days

Work done by A in 1 day = 1/9

Work done by B in 1 day = 1/12

Work done in first 2 days = 1/9 + 1/12 = 7/36

Work done in 10 days = 35/36

Work remaining = 1 - 35/36 = 1/36

Time taken by A to complete the remaining work = 9 * 1/36 = 1/4

So the whole work will be done in 10 + 1/4 = 10 1/4 days