A and b can complete a piece of work in 12 days and 18 days respectively. A begins to do the work and they work alternately one at a time for one day each. The whole work will be completed in? Select one:
a. None of these
b. 7.2 days
c. 14.2 days
d. 15 days
Answers
Answered by
1
Answer:
ans .. a none of these,,,,, 14 (1/3) days
Step-by-step explanation:
hope. it's help.