A and B can complete a piece of work in 15 days. They started work together but after 5 days A left the work .If B completed remaining work in 15 days how many days A can complete the work

Answers

Answered by monikamondokar
0

Step-by-step explanation:

work ofA+B=5×2=10 units

work left 30−10=20 units

A will complete this work in 202 = 10 days

Total time 10days+2 days

= 12 days