Math, asked by Hari4774, 1 year ago

A and b can complete a work in 15 and 10days they started doing the work together but after 2 days b had to leave and a alone can complete the remaining work the whole work

Answers

Answered by psjain
1

a can do the whole work in 15 days , therefore a's one day work = 1/15

b can do the whole work in 10 days ; therefore b's one day work =1/10

a+b one days work = 1/15+1/10

a and b work together for two days ; therefore in two days they do

2/15+2/10 part of work = 10/30= 1/3

After two days b leaves ; therefore part of work left to do...1-1/3=2/3

a does full work in 15 days; therefore a does 2/3 of remaining work in

2/3*15=10 days

Hope this helps!!