A and B can do a piece of work in 10 days B and C in 15 days and C and A in 20 days they all work at it for 6 days and then A leaves and B and C go on together for 4 days more if B then leaves how long will C take to complete the work
Answers
Answered by
1
Since we have given that
Number of days in which A and B can do a piece of work = 12 days
Number of days in which B and C can do a piece of work = 15 days
Number of days in which C and A can do a piece of work = 20 days
L.C.M of 12, 15, 20 = 60
Number of units done by A and B = 60/12=5
Number of units done by B and C = 60/15=4
Number of units done by C and A =60/20=3
Number of days all A, B and C take together is given by
60x2/5+4+3
=120/12
=10
Hence, A, B, and C together take 10 days to complete a piece of work.