A and B can do a piece of work in 10 hours B and C can do it in 15 hours while A and C take 12 hours to complete the work be independently can complete the work in
Answers
Answered by
1
Answer:
A+B's One day work=1 / 10
B+C's one day work=1 / 15
A+C's one day work=1 / 12
A+B +C's 2 days work=1/10 +1/15 +1/12
A+B+C's 2days work=6/60+4/60+5/60
=15/60=1/4
A+B+C's one day work=1/8
A can complete:
1/8-1/15=15-8/120 = 7/120
B can complete:
1/8-1/12=12=8/96=1 / 12
Ccan Complete:
1/8-1/10=10-8/80=1/40
A in 17 1/7 days. Ans
B in 12 days. Ans
C in 40 days. Ans