Math, asked by sweengrover82, 11 months ago

A and B can do a piece of work in 15 days. A alone can finish it in 20 days. How many days will B alone take to finish the same work

Answers

Answered by smsalomte46
3

Answer:

25

Step-by-step explanation:

As work done by A+B=15 days,

& Work done by A alone=20 days, means B can help A to do 5days work

Therefore B alone will take (Work done by A+B) + (Work done by B alone)=

which equals to 20+5=25!

Answered by TheNightHowler
61

Answer :-

B alone can finish the same work in 60 days.

Explanation :-

Since A alone can finish the work in 20 days,

° Work done by A in 1 day = 1/20

Let B does the same work in 'x' days.

° Work done by B in 1 day = 1/x

Work done by A and B in 1 day = 1/20 + 1/x

According to the question,

 =  > 15( \frac{1}{20}  +  \frac{1}{x} ) = 1 \\  =  > 15( \frac{x + 20}{20x} ) = 1 \\  =  > 15x + 300 = 20x \\  =  > 300 = 20x - 15x \\  =  > 300 = 5x \\  =  > x =  \frac{300}{5}  \\  =  > x = 60 \: days

Hence, B alone can finish the same work in 60 days.

Similar questions