A and B can do a piece of work in 15 days. A alone can finish it in 20 days. How many days will B alone take to finish the same work
Answers
Answered by
3
Answer:
25
Step-by-step explanation:
As work done by A+B=15 days,
& Work done by A alone=20 days, means B can help A to do 5days work
Therefore B alone will take (Work done by A+B) + (Work done by B alone)=
which equals to 20+5=25!
Answered by
61
Answer :-
B alone can finish the same work in 60 days.
Explanation :-
Since A alone can finish the work in 20 days,
•°• Work done by A in 1 day = 1/20
Let B does the same work in 'x' days.
•°• Work done by B in 1 day = 1/x
Work done by A and B in 1 day = 1/20 + 1/x
According to the question,
Hence, B alone can finish the same work in 60 days.
Similar questions