A and B can do a piece of work, in 15 days and 20 days respectively
Find (i) The work done by A in 3 days
(ii) The work left after A has worked for 3 days.
(iii) The number of days that B will take to complete the remaining work.
Answers
Answered by
2
Answer:
1. 1/5 part
2. 4/5 part
3. 16
Answered by
1
Answer:
Step-by-step explanation
i) 1/15 × 3 = 1/5
ii) The work left = 1/15 × 12 = 4/5
iii) No. of days B will take to complete the work = 4/5 × 20 = 16 days.