A and B can do a piece of work in 30 days. While B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ?
Answers
Answered by
1
Answer:
(A + B)’s one days’ work = 1/30
(B + C)’s one days’ work = 1/24 .....(1)
(C + A)’s one days’ work = 1/20
Therefore (A + B + C)’s one days’ work
(A + B + C)’s 10 days’ work
= 10/6 = 5/8
From (1) and (2), A's one days’ work
= 1/16 – 24
= 1/48
Therefore remaining 3/8 of the work is done by A alone in 3/8 × 48
= 18 days.
Answered by
2
Answer:
- A + B= 1/30 of the job or A=1/30-B
- A + C= 1/20 of the job or A=1/20-C
- C + B= 1/24 of the job or C=1/24-B
- 1/30-B =1/20-1/24 + B
- B = (1/30 - 1/20 + 1/24 ) / 2
- So B = 1/ 80
- Then we find C = 1/24–1/80 = (20 - 6) /480 = 14/480
- C = 7/240
- then we find A=1/30-B = 1/30 -1/ 80
- A = 5 /240
- Now with their rendiment in ten days they do together:
- = 10 × ( 5/240 + 1/80 + 7/ 240)
- = 15/24
- What is left to do is by A only is:
- 1- 15/24 = 3/8 of the job
- Since A does 5/ 240 per day we calculate:
- X = (3/8) / (5/240)
- X= 18
please do follow me buddy
Similar questions