Math, asked by third42, 5 months ago

A and B can do a piece of work in 30 days. While B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ?​

Answers

Answered by Anonymous
1

Answer:

\huge\underline\bold {Answer:}

(A + B)’s one days’ work = 1/30

(B + C)’s one days’ work = 1/24 .....(1)

(C + A)’s one days’ work = 1/20

Therefore (A + B + C)’s one days’ work

 \frac{1}{2} ( \frac{1}{30}  +  \frac{1}{24}  +  \frac{1}{20} ) \\  =  \frac{1}{2}  \times ( \frac{20 + 25 + 30}{600} ) \\  =  \frac{75}{1200}  \\  =  \frac{1}{16}  \:  \:  \:  \:  \:  \:  \: ...(2)

(A + B + C)’s 10 days’ work

= 10/6 = 5/8

From (1) and (2), A's one days’ work

= 1/16 – 24

= 1/48

Therefore remaining 3/8 of the work is done by A alone in 3/8 × 48

= 18 days.

Answered by charusharma64
2

Answer:

  1. A + B= 1/30 of the job or A=1/30-B
  • A + C= 1/20 of the job or A=1/20-C
  • C + B= 1/24 of the job or C=1/24-B
  • 1/30-B =1/20-1/24 + B
  • B = (1/30 - 1/20 + 1/24 ) / 2
  • So B = 1/ 80
  • Then we find C = 1/24–1/80 = (20 - 6) /480 = 14/480
  • C = 7/240
  • then we find A=1/30-B = 1/30 -1/ 80
  • A = 5 /240
  • Now with their rendiment in ten days they do together:
  • = 10 × ( 5/240 + 1/80 + 7/ 240)
  • = 15/24
  • What is left to do is by A only is:
  • 1- 15/24 = 3/8 of the job
  • Since A does 5/ 240 per day we calculate:
  • X = (3/8) / (5/240)
  • X= 18

please do follow me buddy

Similar questions