A and B can do a piece of work in 4 days, while C and D can do the same work in 12 days. In how many days will A, B, C and D do it together?

1. 12 days

2. 4 days

3. 3 days

4. 2 days

5. None of these

Answers

Answered by Anonymous
5

Answer:

hii

your answer is here!

Step-by-step explanation:

A, B, C and D will together take ¼ + 1/12 = 4/12 = 1/3 ⇒ 3 days to complete the work.

option (c) 3 days right answer !

follow me !

Answered by Anonymous
2

A and B can do a work = 4 days

A and B 1 day work = 1/4

C and D can do work = 12

C and D 1 day work = 1/12

A,B,C,and D 1 day together work = 1/4 + 1/12 = (3+1)/12 = 4/12 = 1/3

so A ,B ,C and D togather work = total work /one day work = 1/1/3 = 3 days

option 3 is right .