Math, asked by fabgirlrock, 11 months ago

A and b can do a piece of work in 6 days and 12 days respectively. They ( both) will complete the work in how many days?

Answers

Answered by warylucknow
4

Answer:

It will take A and B together 4 days to complete the work.

Step-by-step explanation:

The work can be done by A alone in 6 days.

The work can be done by B alone in 12 days.

A's one day work is, \frac{1}{6}.

B's one day work is, \frac{1}{12}.

Compute the work done by them together in 1 day as follows:

\frac{1}{A}+\frac{1}{B} =\frac{1}{6}+\frac{1}{12}=\frac{3}{12} =\frac{1}{4}

Then the number of days it will take both to complete the work is:

No.\ of\ days=1/(\frac{1}{A}+\frac{1}{B}) =1/\frac{1}{4}=4

Thus, it will take A and B together 4 days to complete the work.