A and b can do a piece of work in 6 days and 12 days respectively. They ( both) will complete the work in how many days?
Answers
Answered by
4
Answer:
It will take A and B together 4 days to complete the work.
Step-by-step explanation:
The work can be done by A alone in 6 days.
The work can be done by B alone in 12 days.
A's one day work is, .
B's one day work is, .
Compute the work done by them together in 1 day as follows:
Then the number of days it will take both to complete the work is:
Thus, it will take A and B together 4 days to complete the work.