A and B can do a piece of work in 72 days: B and C can do it in 120 days: A and C can
do it in 90 days in what time can A alone do it?
A) 80days
B) 100 days
C) 120 days
D) 150 days
Answers
Answered by
1
Answer:
option B
Explanation:
According to question,
(A + B)’s one day’s work = \frac{1}{72}
(B + C)’s one day’s work = \frac{1}{120}
and (C + A)’s one day’s work = \frac{1}{90}
On adding all three,
2 (A + B + C)’s one day’s work = \frac{1}{72}+ \frac{1}{120}+ \frac{1}{90}
= \frac{5+3+4}{360} = \frac{1}{30}
∴ (A + B + C)’s one day’s work = \frac{1}{60}
∴ A, B and C together can finish the whole work in 60 days.
Hence option [B] is the right answer