Math, asked by krishnagupta4717, 1 year ago

A and B can do a piece of work in 9 days, B and
C can do it in 12 days and A and C can do it in 18
days. If A, B and C work together, then the work
would be finished in
(1) 6 days (2) 7 days
(3) 8 days (4) 4 days


rk860341: (3)

Answers

Answered by aryan8246
1
answer is in photo please see it
Attachments:
Answered by rk860341
0

(3)

a+b=1/;9

b+c=1/12

c+a=1/18

a+b+c=1/8