A and B can do a work in 10 days, B and C in
12 days while C and A in 15 days. How long
would they take if they all three work together.
Answers
Answered by
0
Answer:
we will first need to know the average
that's sum of days/number of time
Answered by
3
Therefore, it will take 8 days if they all three work together to complete it.
Hope it helps you
Attachments:
![](https://hi-static.z-dn.net/files/d46/2a34c8f56f68d676eb1abb46abc9b531.jpg)
deep428:
answer is 8 days