A and B can do a work in 12 days
and 16 days respectively. Both
worked together for 3 days and then
A left the work and C joined. Both B
and C completed the rest of the work
in 3 days. In how many days C can
complete the whole work?​

Answers

Answered by NaturalStarNehru
1

Answer:

8 days

Please mark me as Brilliant ☺️