Math, asked by achut2268, 2 months ago

A and B can do a work in 12 days and 27 days more respectively then A and B working together. How long will B take to finish the work alone?​

Attachments:

Answers

Answered by amitnrw
0

Given : A and B can do a work in 12 days and 27 days more respectively then A and B working together  

To Find : How long will B take to finish the work alone?​

40 days

45 days

50 days

55 days

Solution:

Let say A & B can complete the work together in   X days

Then A can complete the Work in X  + 12 days

Then B can complete work in X + 27 days

Work in 1 day by both = 1/X

work in 1 day by A = 1/(X + 12)

Work in 1 day by B = 1/(X + 27)

=> 1/X  = 1/(X + 12)  + 1/(X + 27)

=> (X + 12)(X + 27)  =  X (X + 27)  + X(X + 12)

=> X² + 39X + 324   = X² + 27X  + X² + 12X

=> 324 =  X²

=> X = 18

B can complete work in X + 27 days

=> 18 + 27  = 45 Days

B will take 45 days to finish the work alone.

Learn More :

A,b,c can do a piece of work in 150 days,75 days,75/2 days ...

https://brainly.in/question/8268307

a and b can finish a certain piece of work in 4days.if a reduces his ...

https://brainly.in/question/9815966

A and B can do a piece of work in 40 days. He works at it for 8 days ...

https://brainly.in/question/1653764

Answered by ZAYNN
0

Answer:

Let (A + B) can do work in n days.

  • A can do = (n + 12) days
  • B can do = (n + 27) days

⇒ (A + B)'s work = (A × B) / (A + B)

⇒ n = (n + 12)(n + 27) / (n + 12) + (n + 27)

⇒ n = n² + 39n + 324 / 2n + 39

⇒ n(2n + 39) = n² + 39n + 324

⇒ 2n² + 39n = n² + 39n + 324

⇒ 2n² + 39n - n² - 39n = 324

⇒ n² = 324

  • Square Root both sides

⇒ n = 18

B will finish work alone :

⇢ B = (n + 27) days

⇢ B = (18 + 27) days

B = 45 days

Hence, Option 2 ) 45 days is correct.

Similar questions