A and b can do a work in 8 days, b and c can do the same work in 12 days. A, band c together can finish it in 6 days. A and c together will do it in:

Answers

Answered by Anonymous
0
(a+b) 1 day work = 1/8

(b+c) 1 day work = 1/12

a+c) 1 day work = 1/6

now together they all will do in = 2(1/8+1/12+1/6) = (3+2+4/24) = 9/24 = 3/8 = 6/8

hence , 3/4 days will take by them together complete the work