Math, asked by nitinthecursor5738, 1 year ago

A and b can do a work in 8 days, b and c can do the same work in 12 days. A, b and c together can finish it in 6 days. A and c together will do it in : zigya

Answers

Answered by karnanivinay
0
a and b can do the work in 8 days
so in 1 day work done by a And b
 =  \frac{1}{8}
b and c can do work in 12 days
so in 1 day work done by b and c
 =  \frac{1}{12}
a, b and c can do work in 6 days
so in 1 day work done by a, b and c
 =  \frac{1}{6}
work done by a and b in 1 day is 1/8
and done by a, b and c is 1/6
so one day work of c
= 1/6-1/8=8-6/48=2/48=1/24
similarly work done by a in one day
1/6-1/12=12-6/72=1/12
so a one day work is 1/12
c one day work is 1/24
in 1 day they both do work
=
 \frac{1}{12}  +  \frac{1}{24}  \\  =  \frac{2 + 1}{24} \\  =  \frac{3}{24}  \\  =  \frac{1}{8}  \\
so in one day they do 1/8 work
so they complete work in 8 days...