A and b can do piece of work in 7 days with the help of c they finished work in5 days, c alone can do the piece of work in ?
Answers
Answered by
0
Answer:
A + B = 7
A + B + C = 5
= C = Can complete 2 days more than time taken by A and B
Therefore C can complete the work in 9 days