A and b can finish a piece of work in 40 days. b and c in 60 days and c and a in 80 days. in how many days will a alone finish the job? .

Answers

Answered by Ravijot
0
I think 'a' will take 30 days
Answered by perambhanu4
5

Answer:

Step-by-step explanation:

A+B=1/40

B+C=1/60

C+A=1/80

2(A+B+C)=13/240

A+B+C=13/480

A=13/480-1/60

A=1/96

A alone done 96 days