Math, asked by aditi11choudhary22, 8 months ago

A and B can finish a piece of work in 6 days and 4 days, respectively, working alone.
A started the work. After 2 days, he was joined by B. Find the time taken to finish the
remaining work.​

Answers

Answered by farhatshamim303
3

Step-by-step explanation:

Given that A can finish a piece of work in 6 days,

So, in one day A will do 1/6 th of work,

Given that B can finish a piece of work in 4 days,

So, in one day B will do 1/4 th of work,

Given that initially A has worked for 2 days,

So A will complete 2*1/6 = 1/3 rd of work

Remaining Work = 2/3 rd of work.

If A and B works together,

In 1 day, bot A and B could do = (1/6 + 1/4) of work

= 5/12 th of work

So, 2/3 rd of work requires 2/3*1/(5/12)

= 8/5 days,

Total time , to finish the work

= Time A working alone an Time taken when both A and B are

working together

= 2 + 8/5

= 18/5 days

Hope, it helps !

Answered by Anonymous
2

Answer:

{\huge{\underline{\bold{\red{Given:-}}}}}

that A can finish a piece of work in 6 days,

{\huge{\underline{\bold{\green{so,}}}}}

in one day A will do 1/6 th of work,

{\huge{\underline{\bold{\red{Given:-}}}}}

that B can finish a piece of work in 4 days,

{\huge{\underline{\bold{\green{so,}}}}}

in one day B will do 1/4 th of work,

{\huge{\underline{\bold{\red{Given:-}}}}}

that initially A has worked for 2 days,

{\huge{\underline{\bold{\green{so,}}}}}

A will complete 2×1/6 = 1/3 rd of work

{\huge{\underline{\small{\bold{\pink{remaining\:work:-}}}}}}

2/3 rd of work.

⇒If A and B works together,

⇒In 1 day, bot A and B could do = (1/6 + 1/4) of work

⇒ 5/12 th of work

{\huge{\underline{\bold{\pink{So,}}}}}

2/3 rd of work requires 2/3×1/(5/12)

⇒ 8/5 days,

{\huge{\underline{\small{\bold{\red{total\:time,\:to\: finish\:the\:work:-}}}}}}

⇒Time A working alone an Time taken when both A and B are

{\huge{\underline{\small{\bold{\pink{working\: together:-}}}}}}

⇒ 2 + 8/5

⇒ 18/5 days

{\huge{\underline{\small{\bold{\blue{hope\:help \:u:)}}}}}}

Similar questions