Math, asked by penumakarebekah07, 9 months ago

A and B can finish a work in 20 days and 60 days respectively. A started to work, after 10 days B joined him. How much time will they take to complete the remaining work ?​

Answers

Answered by orchidravi3
1

Answer:

Given,

A can complete a work in 20 days

A's one day work =1/20

B can complete a work in 60 days

B's one day work =1/60

(A+B) = 1/20 + 1/60

= 3+1/60

= 4/60

= 1/15

So,

A and B can complete the work in 15 days

It is given that A started the work,after 10 days B's joined him

So,

Work done by A after 10 day = 1/15 × 10

= 2/3

Now,

we have to find the remaining work

=2/3 - 1

= 1/3

Hence,

they will complete the work in 3 days

Answered by TooFree
4

Given:

A can do the work in 20 days

B can do the work in 60 days

A worked for 10 days and then B joined in.

To Find:

Time taken to complete the remaining work

Solution:

A can do the work in 20 days

⇒ A can do 1/20 of the work in 1 day

B can do the work in 60 days

⇒ B can do 1/60 of the work in 1 day

Find the amount of work done in a day by A and B

Work = 1/20 + 1/60

Work = 1/15

Find the amount of work completed in the first 10 days by A:

Work completed = 1/20 x 10

Work completed = 1/2

Find the amount of work left after 10 days:

Work left = 1 - 1/2

Work left = 1/2

Find the number of days needed to finish the remaining work:

Number of days needed = 1/2  ÷ 1/15

Number of days needed =7.5

Answer: They will need 7.5 days to complete the remaining work.

Similar questions