A and B can together complete a work in 10 days. A alone can do it in 18 days. How long would B
alone take to complete the work?
Answers
Answered by
1
Step-by-step explanation:
In 10 days A + B can so = 1 work
In 1 day A+B can do = 1/10 work
In 15 days A can do = 1 work
In 1 day A can do = 1/15 work
Let in x days B can do = 1 work
so in 1day B can do 1/x work
In 1 day A+B can do = 1/10 work
1/15 + 1/x = 1/10
1/x = 1/10 - 1/15
1/x = 1/30
x = 30