A and B completed a work together in 5 days. Had
A worked at twice the speed and B at half the speed,
it would have taken them four days to complete the
job. How much time would it take for A alone to do
the work?
(a) 10 days
(b) 20 days
(c) 25 days
(d) 15 days
Answers
Answered by
0
Answer:
A and B completed a work together in 5 days. had A worked at twice the speed and B at half the speed, it would have taken them four days to complete the job. How much time would it take for A alone to do the work?
A. 10 days
B. 20 days
C. 25 days
D. 15 days
E. 24 days
Answer: Option A
Answered by
0
Answer:
please mark it brainliest option a
Step-by-step explanation:
Assume work to be done 100%.
First case,
A + B = 100/5 = 20% work done per day -------- (1)
Second case,
2A + B/2= 100/4 = 25% work done per day ------ (2)
On solving equation (1) and (2), we get
A = 10 days