Math, asked by gatiyalap1221, 1 year ago

A and b takes 6 hours and 9 hours respectively to conpletr a work. a work for 1 hour and then b works for two hours how much work is done in these 3 hours

Answers

Answered by chaitanyakrishn1
2
A 's 1 hour work = 1/6

B's 1 hour work = 1/9

B's 2 hour work = 2/9

Therefore portion of work done = 1/6 + 2/9 = (3+4) /18 = 7/18