A and b togeather can complete a work in 12 days and b and c can do it in 16 days. A work for 5 days and b for 7 days then c complete the remaining work in 13 days. In how many days b can finish the work
Answers
Answered by
0
Answer:
48 Days
Please mark the answer as "The Brainliest answer" if you like it
Step-by-step explanation:
let say w work was to be done then
12a + 12b = w
16b + 16c = w
5a + 7b + 13c = w
5(w-12b)/12 + 7b + 13(w-16b)/16 = w
5(w-12b)*4 + 48*7b + 13(w-16b)*3 = 48w
20w - 240b + 336b + 39w - 624b = 48w
59w - 48w = 624b + 240b -336b
11w = 528b
w = 48b
so b will take 48 days to finish work