A and b together can complete a task in 7 days. b alone can do it in 20 days. what part of the work was carried out by a? i. a completed the job alone after a and b worked together for 5 days. ii. part of the work done by a could have been done by b and c together in 6 days.
Answers
Answered by
3
18 days..............