Math, asked by Harshrajesh5746, 1 year ago

A and b together can complete a work in 3 days. they start together. but, after 2 days, b left the work. if the work is completed after 2 more days, b alone could do the work in

Answers

Answered by danielochich
0
a and b complete 1/3 of the work in one day

in 2 days, they complete 2 x 1/3 = 2/3 of the work

the remaining fraction is 1/3

a takes 2 more days to complete the work

the rate at which a is working = (1/3) / 2 = 1/6 per day


In the first 2 days, a completed 1/6 x 2 = 1/3 of the work

b completed 2/3 - 1/3 = 1/3

the rate at which b is working = (1/3) / 2 = 1/6 per day 

b alone could take 6 days to complete the work
Answered by Anonymous
3

Answer:

Step-by-step explanation:

a and b complete 1/3 of the work in one day

in 2 days, they complete 2 x 1/3 = 2/3 of the work

the remaining fraction is 1/3

a takes 2 more days to complete the work

the rate at which a is working = (1/3) / 2 = 1/6 per day

In the first 2 days, a completed 1/6 x 2 = 1/3 of the work

b completed 2/3 - 1/3 = 1/3

the rate at which b is working = (1/3) / 2 = 1/6 per day

b alone could take 6 days to complete the work

Similar questions