Math, asked by akanksha2009, 6 months ago

A and B together can do a piece of work in 12 days, which Band C together can do in
16 days. After A has been working at it for 5 days and B for 7 days, C finishes in 13 days. In how
many days C alone will do the work?
(A) 16
(B) 24
(C) 36
(D) 48

Answers

Answered by tripathysoumya3
0

Answer:

36 days

Step-by-step explanation:

using linear equation its solved

Answered by khashrul
1

Answer:

Correct option is (B) 24

Step-by-step explanation:

A and B together can do a piece of work in 12 days.

∴ A and B together each day can complete \frac{1}{12} part of the work.

Similarly, B and C together each day can complete \frac{1}{16} part of the work

Let's assume A can do it in x days, i.e. in each day A can complete \frac{1}{x} part

Let's also assume B can do it in y days.  In each day B can complete \frac{1}{y} part

Let's also assume C can do it in z days.  In each day C can complete \frac{1}{z} part

According to the problem:

\frac{1}{x}  + \frac{1}{y}  = \frac{1}{12}

and \frac{1}{y}  + \frac{1}{z}  = \frac{1}{16}

and [1 - (\frac{5}{x} + \frac{7}{y})] = \frac{13}{z}

=> 1 - 5(\frac{1}{x}  + \frac{1}{y}) - \frac{2}{y} - \frac{2}{z} = \frac{11}{z}

=> 1 - \frac{5}{12} - \frac{2}{16} = \frac{11}{z}

=> \frac{48 - 20 -6}{48} = \frac{11}{z}

=>\frac{22}{48} = \frac{11}{z}

∴ z = 24

∴ Correct option is (B) 24

Similar questions