Math, asked by paulprarthana777, 5 months ago

A and B together can do a piece of work in 15 days, while B alone can finish it 20 days. In how

many days can A alone finish the work ? (Page 3/5)

Example 5: A and B can do a piece of work in 15 days and 20 days respectively. Find:

(i) The work done by A in 3 days .

(ii) The work left after A has worked for 3 days.

(iii) The number of days that B will take to complete the remaining work.​

Answers

Answered by SiddharthArya
2

Step-by-step explanation:

let’s say entire work is done means he/she has done 100% of the work.

Reasonably, according to the statement,A alone can complete only 5% of the work per day. (100/20=5)

A +B worked for 15 days→ A completed 15*5=75% of the work . Thus , rest 25% work has been completed by B in 15 days.

B has done 25% of the work in 15 days. Thus, he would take 60 days to complete the whole work. (15 *4=60)

Second way:

If you are really good at maths: It is a simple equation.First consider 1 day of work.

A→1/20

B→ Don’t know

A+B=1/15.

Thus, 1/20+1/B=1/15. If you solve this B would get 60. ( you need to be very strong in maths by watching the equation to find out 60 for B).

So in one day B would complete 1/60th work . To complete entire work he would take 60 days.

Similar questions