A and B together can do a piece of work in 40 days. A having worked for 20 days, B finishes the remaining work alone in 60 days. In How many days shall B finish the whole work alone?

A) 60 B) 70 C) 80 D) 90

Answers

Answered by Hoyden
0

Answer:

Step-by-step explanation:

60

Answered by trmanormak
0

Answer: (C) 80

Explanation:

Let A's 1 day's work=x and B's 1 day's work=y

Then x+y = 1/40 and 20x+60y=1

Solving these two equations , we get : x= 1/80 and y= 1/80

Therefore B's 1 day work = 1/80

Hence,B alone shall finish the whole work in 80 days