A and b together can do a piece of work in 40 days. A having worked for 20 days, b finishes the remaining work alone in 60 days. In how many days shall b finish the whole work alone
Answers
Answered by
1
Answer:
Step-by-step explanation:
a+b=40
A+b in one day=1/40
A in 1day=1/40-b=1-40b/40
A in 20 days=1-40b/40*20=1-40b/2
remaining work=1-(1-40b)/2=(1+40b)/2
B did remain work in 60days
1+40b/2 work in 60 days
wOrk done in 1 day=1+40b/120
=>b=1+40b/120
=>120b=40b+1
=>80b=1
b=1/80 work in 1 day so he will finish in 80 days
mArk it brainliest
Answered by
2
HEY Buddy...!! here is ur answer
Answer : 80 days
Let, work of A of 1 day = x and work of B of 1 day = y
Also Given that A worked for 20 days and B finished the remaining work in 60 days.
According to the question :
On solving these equations :
On Multiplying by 20 in equation (1)
On subtracting equation (2) from (3)
On putting the value of y in equation (1)
So, the work of A and work of B of 1 day = 1/80
It mean they both can complete the whole works in 80 days.
I hope it will be helpful for you...!!
THANK YOU ✌️✌️
Answer : 80 days
Let, work of A of 1 day = x and work of B of 1 day = y
Also Given that A worked for 20 days and B finished the remaining work in 60 days.
According to the question :
On solving these equations :
On Multiplying by 20 in equation (1)
On subtracting equation (2) from (3)
On putting the value of y in equation (1)
So, the work of A and work of B of 1 day = 1/80
It mean they both can complete the whole works in 80 days.
I hope it will be helpful for you...!!
THANK YOU ✌️✌️
Similar questions