Math, asked by rockpartyHARSH2252, 9 months ago

A and B together can finish a piece of work in 12 days . If A alone can finish the same work in 20 days, in how many days B alone can finish it

Answers

Answered by ExᴏᴛɪᴄExᴘʟᴏʀᴇƦ
42

\huge\sf\pink{Answer}

☞ B alone will get the work done in 30 days

\rule{110}1

\huge\sf\blue{Given}

✭ A and B can finish a piece of work in 12 days

✭ A alone can finish the same work in 20 days

\rule{110}1

\huge\sf\gray{To \:Find}

✭ Time taken by B to complete the same work?

\rule{110}1

\huge\sf\purple{Steps}

\bullet\:\underline{\textsf{As Per the Question}}

☯ If A and B can finish the work in 12 days,then,

\sf 1 \ day = \dfrac{1}{12} of the work

Now the time that A will take to finish the work in a day

»» \sf 1 \ day = \dfrac{1}{20} of the work

So then the amount of work that can be done by B will be,

\sf 1 \ day = Total \ Work - Work \ by \ A

\sf 1 \ day = \dfrac{1}{12} - \dfrac{1}{20}

\sf\red{\dfrac{1}{30}}

Finally the time that B will take to complete his work alone will be,

\sf \dfrac{1}{30} of the work = 1 day

\sf 1\times 30

\sf\orange{B =30 \ days}