a and b together can finish a piece of work in 12 days.if a alone can finish the same work in 20 days in how many days b alone can finish it?
Answers
Answered by
3
A and B can do the work in 12 days
work in one day= 1/12 part
A can do the work in 20 days
work in one day=1/20 part
So,
B's one day work=
=A and B's 1 day work- A's one day work
=1/12-1/20
=(5-3)/60
=1/30
Time taken by B to complete the work=1/(1/30)days
=30 days
Answered by
0
Answer:
we will subtract work of a from work of both a and b
first we will take reciprocals
the answer will be 30 days