A and B together can paint a room in 18 days. They work together for 8 days and then B goes away. A finishes the rest of work in 15 days. How long would each take to finish the work separately?
Answers
A will alone take 27 days to paint a room and B alone will take 54 days to finish the same work.
Step-by-step explanation:
A and B together can paint a room in 18 days
So, work done by (A+B) in 1 day =
∵ They have worked together for only 8 days
∴ Work done by (A+B) in 8 days =
∴ The remaining amount of work = 1 - ← done by A alone in 15 days
So,
If th work is done by A alone in 15 days
Then, 1 work will be done by A in = 15 × = 3 × 9 = 27 days
∴ Work done A alone in 1 day =
Now,
The work done By B alone to finish the same work will be given by,
= [work done by (A+B) in 1 day] - [work done by A alone in 1 day]
=
=
=
Thus, A would take 27 days and B would take 54 days to finish the work separately.
--------------------------------------------------------------------------------------
Also View:
A and B working together can do a work in 6 days. if A takes 5 days less than B to finish the work in how many days B alone can do the work
https://brainly.in/question/8587762
Vrujesh takes 6 days less to complete one work then Kaushal if Kaushal and vrujesh work together they can finish the work in 4 days in how many days Kaushal can alone finish the work
https://brainly.in/question/14792630
Manish takes 9 days more than his father to do a certain piece of work together they can do the work in 6 days •how many days will Manish take to do that work alone?
https://brainly.in/question/14532722
A alone can finish the work in 27 days
B alone can finish the work in 54 days
Let the total work = x
A and B can together paint in 18 days .
A can finish 10 days work of A and B together in 15 days .
Therefore , 1 day work of A and B = 1.5 days work of A
A can finish the total work alone in = 1.5 × 18 = 27 days
One day work of A and B together = one day work of A + one day work of B
One days work = total work / time taken to complete the work
=> x/18 = x/27 + x/t [t - time taken by B alone to complete the work]
=> 1/18- 1/27 = 1/t
=> t = 54 days
Time taken by B alone = 54 days