A and b together complete job in 8days b alone done in 12days if b worked for 4 days
Answers
Answered by
0
1 day work of b = 1/12
1 day work of a+b together = 1/8
1 day work of a = 1/8 - 1/12
= 1/24
A can do the work alone in 24 days
b worked for 4 days so work done be b = 4/12 = 1/3
remaining work = 1 - 1/3 = 2/3
2/3 work has to be completed by a
so 2/3 of 24 = 16
a will complete the remaining work in 16 days