A and B working together can complete a task in 8 days, whereas B and C working together can complete it in 16 days. A worked at it for 5 days and B worked at it for 6 days. C alone finished the remaining work in 16 days. How many days would C alone take to complete the same work?
Answers
Answered by
0
Answer:
total days is 24
A+B=5+6=11
C= 24-11
C alone take 13 days to complete the same work.