A and B, working together can finish a peice of work in 6 days, while A alone can do it in 9 days. how much time will B alone take to finish it?
Answers
Answered by
0
Step-by-step explanation:
6 days of both A and B finish the work
9 days of only B finishes the work
6A+6B=9B
6A=3B
B works twice as hard (per day) as A
If B takes 9 days alone, then A will require 18 days alone to complete the same work.