. a, b and c can complete a piece of work in 8, 12 and 24 days respectively. a and c started working, and b joined them after one day. if c left 2 days before completion of the work, in how many days was the work finished? (a) days (b) days (c) days (d) days (e) days
AtomicBlonde:
what's with the options, plz fix this
Answers
Answered by
0
a=8
b=11
c=22
so the total days in which the work will be completed be 41 days
b=11
c=22
so the total days in which the work will be completed be 41 days
Answered by
0
Answer:
4 2/3 days
Step-by-step explanation:
take LCM for total work, so total work -24
then calculate efficiency,
A's efficiency-3
B's efficiency-2
C's efficiency-1
so first day: (A+C)= 4 work
last 2 day: (A+B)= (3+2)*2=10 work
therefore, 3 days 14 work completed, the remaining work is 10.
remaining work completed by (A+B+C)=6
so, 10/6= 1 4/6 = 1 2/3
so total days = 1+2+1 2/3 = 4 2/3 days