A, B and C can do a piece of work in
24, 32 and 64 days respectively. They
starts working, A left the work after 6
days while B left the work before 6 days
from the completion of work. In how
many days work will be finished?
A. 20
B. 18
C. 15
D. None of these
Answers
The work will be finished in 20 days, if A leaves after the first 6 days, B leaves before the last 6 days and C does continue to work till the end.
Step-by-step explanation:
Step 1:
It is given that,
A, B & C can do a piece of work in 24, 32 and 64 days respectively.
So, The fraction of work done by each of them in 1 day:
A =
B =
C =
A leaves after 6 days of the start of the work therefore, A, B & C each have worked for 6 days, i.e.,
The fraction of work done by each of them in 6 days is:
A = = ¼
B =
C =
∴ Total fraction of work done in first 6 days =
And
The remaining fraction of work =
Step 2:
Now, B leaves 6 days before the completion of the work, which means that C works alone for 6 days.
So, the fraction of work that C does alone in last 6 days is =
∴ The fraction of work done before B has left =
Let's assume B and C did the th of the work in "x" days.
So, we have
work is done by B and work is done by C.
Therefore, we can write the equation as,
⇒ x *
⇒ x =
⇒ x = 8 days
Thus,
The total days required to finish the work is,
= 6 + 8 + 6
= 20 days
----------------------------------------------------------------------------------------
Also View:
A and B working together can do a work in 6 days. if A takes 5 days less than B to finish the work in how many days B alone can do the work
https://brainly.in/question/8587762
Manish takes 9 days more than his father to do a certain piece of work together they can do the work in 6 days •how many days will Manish take to do that work alone?
https://brainly.in/question/14532722
The correct answer is A. 20 days.
The efficiency of each one is given as follows:
A's =
B's =
C's =
Now A did work for 6 days so total work done by A = =
Let the total work be finished in x days then
Work done by B =
Work done by C =
Total work done = work done by A + work done by B + work done by C
1 = + +
1 =
64 = 3x + 4
3x = 60
x = 20 days