Math, asked by aksgupta2303, 10 months ago

A, B and C can do a piece of work in
24, 32 and 64 days respectively. They
starts working, A left the work after 6
days while B left the work before 6 days
from the completion of work. In how
many days work will be finished?
A. 20
B. 18
C. 15
D. None of these​

Answers

Answered by bhagyashreechowdhury
2

The work will be finished in 20 days, if A leaves after the first 6 days,  B leaves before the last 6 days and C does continue to work till the end.

Step-by-step explanation:

Step 1:

It is given that,

A, B & C can do a piece of work in 24, 32 and 64 days respectively.

So, The fraction of work done by each of them in 1 day:

A = \frac{1}{24}

B = \frac{1}{32}

C = \frac{1}{64}

A leaves after 6 days of the start of the work therefore, A, B & C each have worked for 6 days, i.e.,

The fraction of work done by each of them in 6 days is:

A = \frac{6}{24} = ¼

B = \frac{6}{32} = \frac{3}{16}

C = \frac{6}{64} = \frac{3}{32}

Total fraction of work done in first 6 days = \frac{1}{4} + \frac{3}{16} + \frac{3}{32}  = \frac{8+6+3}{32} = \frac{17}{32}

And

The remaining fraction of work = 1 - \frac{17}{32} = \frac{15}{32}

Step 2:

Now, B leaves 6 days before the completion of the work, which means that C works alone for 6 days.

So, the fraction of work that C does alone in last 6 days is =  \frac{6}{64} = \frac{3}{32}

The fraction of work done before B has left =  \frac{15}{32} - \frac{3}{32}  = \frac{12}{32} = \frac{3}{8}

Let's assume B and C did the \frac{3}{8}th of the work in "x" days.

So, we have

\frac{x}{32} work  is done by B and \frac{x}{64} work is done by C.

Therefore, we can write the equation as,

\frac{x}{32} + \frac{x}{64}  = \frac{3}{8}

⇒ x * \frac{2+1}{64} = \frac{3}{8}

⇒ x = \frac{64}{8}

x = 8 days

Thus,

The total days required to finish the work is,

= 6 + 8 + 6

= 20 days

----------------------------------------------------------------------------------------

Also View:

A and B working together can do a work in 6 days. if A takes 5 days less than B to finish the work in how many days B alone can do the work

https://brainly.in/question/8587762

Manish takes 9 days more than his father to do a certain piece of work together they can do the work in 6 days •how many days will Manish take to do that work alone?

https://brainly.in/question/14532722

Answered by fistshelter
3

The correct answer is A. 20 days.

The efficiency of each one is given as follows:

A's = \frac{1}{24}

B's = \frac{1}{32}

C's = \frac{1}{64}

Now A did work for 6 days so total work done by A = \frac{6}{24} = \frac{1}{4}

Let the total work be finished in x days then

Work done by B = \frac{x-6}{32}

Work done by C = \frac{x}{64}

Total work done = work done by A + work done by B + work done by C

1 = \frac{1}{4} + \frac{x-6}{32} + \frac{x}{64}

1 = \frac{16+2x - 12+x }{64}

64 = 3x + 4

3x = 60

x = 20 days

Similar questions