Math, asked by abratmughal6100, 11 months ago

A, b and c can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but c left 4 days before the completion of the work. In how many days was the work completed? Select one:

a. 11 days

b. 14 days

c. 13 days

d. 12 days

Answers

Answered by streetburner
1

Answer

a. 11 days

Step-by-step explanation:

time work. efficiency

24. 5

30. 120. 4

40. 3

-------------------------

12 = total efficiency

Let the work was completed in x days, then :

12(x-4) + 4*9 = 120

12x - 48 + 36 = 120

12x = 132

x = 11