A, b and c can do a piece of work in 30, 20 and 10 days respectively. A is assisted by b on one day and by c on the next day, alternately. How long would the work take to finish?
Answers
Answered by
6
hope this helps you....
Attachments:
ronilrocky:
Hi
Answered by
3
days Work will be Completed
Step-by-step explanation:
- First day A+B worked = 2+3 = 5 units
- Second Day A + C Worked = 2 + 6 = 8 units
- Third Day A + B Worked = 5 units
- In one cycle work is completed = 13 units
It will continue at last, work will finish in
and 8 units of work is left.
Now, A will do with 'B' and they will complete 5 units.
- Remaining 3 units will be done by A and C in
- Total Time = 4 cycle 2 = 8 days
A + B = 1 days
A + C = days
Thus, Total Time = 8 days + (A+B)'s days + (A+C)'s days
=
= days