A,b and c can do a piece of work in 40 days,30 days and 60 days respectively.A work continuously,on every third day a is assisted by b and
c.In how many days work is completed
Answers
Answered by
2
LCM of 40, 30 and 60 is 120
So we will take total work to be 120 units.
A = 120/40 = 3 units/day
B = 120/30 = 4 units/day
C = 120/60 = 2units/day
Now A is working two days alone and on third day B and C are joining him and this goes on and on until work is done.
Day 1 = A’s work = 3 units
Day 2 = A’s work = 3units
Day 3 = (A + B +C) ‘ s work = 3 + 4 + 2 =9 units
So this is a set of 3 days in which total 3+3+9 = 15units work is being done.
Now to complete 120 units, 120/15= 8 such sets of 3 days are needed.
8 sets of 3 days means 8*3 = 24days