A, B and C can do a piece of work in 6 days, 12 days and 24 days respectively. In what time
will they altogether do it?
Answers
Answered by
6
Answer:
Step-by-step explanation:
If A can do a piece of work in n days, then A's 1 day's work = 1/n
(A+B+C)′s 1day's work=1/6 + 1/12 + 1/24 = 7/24
Formula: If A's 1 day's work = 1/n , then A can finish the work in n days
So, all the three together will complete the job in
24/7 days=3 3/7 days
Answered by
2
Answer:
3 whole 3/7 days
Step-by-step explanation:
A's one day work = 1/6
B's one day work = 1/12
C's one day work = 1/24
Hence, A, B and C's one day work = 1/6 + 1/12 + 1/24 = 7/24
Therefore, A, B and C will do the work altogether in 3 3/7 days.