A, b and c can do a piece of work individually in 8, 12 and 15 days, respectively. a and b start working but a quits after working for 2 days. after this, c joins b till the completion of work. in how many days will the work be completed?
Answers
Answered by
8
a can do a piece of work = 8 days
b can do a piece of work = 12 days
c can do a piece of work = 15 days
a and b start working together ,
together they can do work = 8 × 12/(8 + 12) days = 24/5 days
means together a and b can do 5/24th of work in 1 day .
∴ 5/12th part of work completed in 2days .
now, after two days a quits .
Rest part of work is done by b and c together.
∴ rest part of work = 1 - 5/12 = 7/12th part of work.
But we observed , b and c can do work = 12 × 15/(12 + 15) days = 20/3 days
So, number of days to complete 7/12th part of work = 7/12 × 20/3 = 140/36 days
Hence, b and c together complete the 7/12th part of work = 35/9 days = 3 8/9 days .
b can do a piece of work = 12 days
c can do a piece of work = 15 days
a and b start working together ,
together they can do work = 8 × 12/(8 + 12) days = 24/5 days
means together a and b can do 5/24th of work in 1 day .
∴ 5/12th part of work completed in 2days .
now, after two days a quits .
Rest part of work is done by b and c together.
∴ rest part of work = 1 - 5/12 = 7/12th part of work.
But we observed , b and c can do work = 12 × 15/(12 + 15) days = 20/3 days
So, number of days to complete 7/12th part of work = 7/12 × 20/3 = 140/36 days
Hence, b and c together complete the 7/12th part of work = 35/9 days = 3 8/9 days .
Answered by
19
Hello Dear.
Here is your answer---
→→→→→→→→→→
A's can do a Piece of Work in 8 Days.
A's one Day Work = 1/8 Days
B's can do a Piece of Work in 12 Days.
B's one day work = 1/12 Days.
C's can do a Piece of Work in 15 Days.
C's one day Work = 1/15 Days.
As per as Question, A and B starts the Works Together,
Thus, Time taken by Both to complete the Works =
A's one day work + B's one day work
= 1/8 + 1/12
= (3 + 2)/24 [Taking L.C.M.]
= 5/24
∴ Time taken by A and B to complete the work together = 24/5 Days.
In one Day, the work done by A and B is 5/24 th part of the work.
In 2 Days-------------------------------------------(5/24) × 2 th part of work
= 5/12th Part of the Work.
Thus, Part of the Work that is Remaining = 1 - 5/12
= (12 - 5)/12
= 7/12
After 2 Days, C joins the work..
Thus, work done by B and C in one Day = 1/B + 1/C
= 1/12 + 1/15
= (4 + 5)/60
= 9/60
= 3/20
Thus, Remaining work(7/12th part) will be completed by B and C
=
= 140/36
= 70/18
= 35/9 Days.
Hence, The Total Work will be Done in (2 Days + 35/9 Days)
= (18 + 35)/9 Days.
= 53/9 Days.
= Days.
Thus, the Total time taken will be Days.
→→→→→→→→→→
I Anticipate it will helps u.
Have a Marvelous Days.
Here is your answer---
→→→→→→→→→→
A's can do a Piece of Work in 8 Days.
A's one Day Work = 1/8 Days
B's can do a Piece of Work in 12 Days.
B's one day work = 1/12 Days.
C's can do a Piece of Work in 15 Days.
C's one day Work = 1/15 Days.
As per as Question, A and B starts the Works Together,
Thus, Time taken by Both to complete the Works =
A's one day work + B's one day work
= 1/8 + 1/12
= (3 + 2)/24 [Taking L.C.M.]
= 5/24
∴ Time taken by A and B to complete the work together = 24/5 Days.
In one Day, the work done by A and B is 5/24 th part of the work.
In 2 Days-------------------------------------------(5/24) × 2 th part of work
= 5/12th Part of the Work.
Thus, Part of the Work that is Remaining = 1 - 5/12
= (12 - 5)/12
= 7/12
After 2 Days, C joins the work..
Thus, work done by B and C in one Day = 1/B + 1/C
= 1/12 + 1/15
= (4 + 5)/60
= 9/60
= 3/20
Thus, Remaining work(7/12th part) will be completed by B and C
=
= 140/36
= 70/18
= 35/9 Days.
Hence, The Total Work will be Done in (2 Days + 35/9 Days)
= (18 + 35)/9 Days.
= 53/9 Days.
= Days.
Thus, the Total time taken will be Days.
→→→→→→→→→→
I Anticipate it will helps u.
Have a Marvelous Days.
Similar questions
English,
8 months ago
English,
8 months ago
Math,
8 months ago
Social Sciences,
1 year ago
Science,
1 year ago